[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253610":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1253610,838,1,"单选题","通过流水作业方法、科学排序方法、网络计划方法、滚动计划方法和电子计算机辅助进度管理等控制项目进度的方法属于（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","行政方法",false,{"key":16,"text":17,"correct":14},"B","经济方法",{"key":19,"text":20,"correct":21},"C","管理技术方法",true,{"key":23,"text":24,"correct":14},"D","其他方法","通过流水作业方法、科学排序方法、网络计划方法、滚动计划方法和电子计算机辅助进度管理等控制项目进度的方法属于管理技术方法。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]