[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253607":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1253607,838,1,"单选题","在调整施工进度计划时，采用改善外部配合条件，改善劳动条件，实施强有力的调度等是属于（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","组织措施",false,{"key":16,"text":17,"correct":14},"B","技术措施",{"key":19,"text":20,"correct":21},"C","经济措施",true,{"key":23,"text":24,"correct":14},"D","其他配套措施","在调整施工进度计划时，采用改善外部配合条件，改善劳动条件，实施强有力的调度等是属于经济措施。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]