[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253606":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1253606,838,1,"单选题","在调整施工进度计划时，采用增加工作面，组织更多的施工队伍；增加每天的施工时间；增加劳动力和施工机械的数量是属于（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","组织措施",true,{"key":16,"text":17,"correct":18},"B","技术措施",false,{"key":20,"text":21,"correct":18},"C","经济措施",{"key":23,"text":24,"correct":18},"D","其他配套措施","在调整施工进度计划时，采用增加工作面，组织更多的施工队伍；增加每天的施工时间；增加劳动力和施工机械的数量是属于组织措施。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]