[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253599":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1253599,838,1,"单选题","甲公司总承包某超高层五星级酒店工程，并将其中的机电安装工程分包给乙公司完成，其电力供应的干线为电力电缆，电力电缆从地下一层的变配电室经电缆沟通至多个电缆竖井，再经电缆竖井至各层的分配电箱，电缆数量大、规格多、路径曲折，部分电缆出竖井后经导管或桥架到用电点，为此项目部制定编写了电缆敷设专项方案用于施工，保证了电缆敷设的顺利进行。根据背景资料，回答下列问题。 下列有关电缆敷设的说法错误的是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","有条件的最好自下而上敷设",true,{"key":16,"text":17,"correct":18},"B","敷设时，同截面电缆应先敷设低层，后敷设高层，要特别注意，在电缆轴附近和部分楼层应采取防滑措施",false,{"key":20,"text":21,"correct":18},"C","电缆敷设严禁有绞拧、铠装压扁、护层断裂和表面严重划伤等缺损",{"key":23,"text":24,"correct":18},"D","电缆敷设时，应敷设一根立即整理一根、卡固一根","电缆敷设，有条件的最好自上而下敷设，将电缆吊至楼层顶部，从顶部开始向下敷设。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]