[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253594":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1253594,838,1,"单选题","案例一A公司接到B公司的施工总进度计划后，应策划价值设备安装施工接到计划：第三阶段是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","与土建工程施工全面配合阶段",false,{"key":16,"text":17,"correct":14},"B","全面安装的高峰阶段",{"key":19,"text":20,"correct":21},"C","安装工程由高峰转入收尾，全面进行试运转阶段",true,{"key":23,"text":24,"correct":14},"D","安装工程结束阶段","A公司接到B公司的施工总进度计划后，应策划价值设备安装施工接到计划：第一阶段是与土建工程施工全面配合阶段；第二阶段是全面安装的高峰阶段；第三阶段是安装工程由高峰转入收尾，全面进行试运转阶段。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]