[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253593":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1253593,838,1,"单选题","建筑电气工程中，无论何种情况，防雷接地的（ ）要排在最末端。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","接地干线敷设",false,{"key":16,"text":17,"correct":14},"B","引下线敷设",{"key":19,"text":20,"correct":21},"C","接闪器安装",true,{"key":23,"text":24,"correct":14},"D","接地极埋设","建筑电气工程中，无论何种情况，防雷接地的接闪器安装要排在最末端。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]