[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253582":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1253582,838,1,"单选题","施工方案比较的方法为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","定性和定量",true,{"key":16,"text":17,"correct":18},"B","解析和分析",false,{"key":20,"text":21,"correct":18},"C","次要和重要",{"key":23,"text":24,"correct":18},"D","技术和经济","施工方案比较通常用技术和经济两个方面进行分析，方法为定性和定量两种，定量分析要大量的数据积累，这些数据是随着时间和技术进步而变动的。定性分析要有较多的经验积累，这些经验不仅有个人的，更主要是团队的项目管理班子集体的。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]