[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253580":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1253580,838,1,"单选题","施工方案比较，重要性比较包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","技术效率",false,{"key":16,"text":17,"correct":14},"B","创新程度",{"key":19,"text":20,"correct":21},"C","推广应用价值",true,{"key":23,"text":24,"correct":14},"D","投资额度","具体比较要从三个方面入手：即技术先进性比较，包括创新程度、技术效率、安全可靠程度等；经济合理性比较，包括投资额度、对环境影响程度、对工程进度影响、性价比等；重要性比较，包括推广应用价值、资源节约、降低污染等社会效益。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]