[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253551":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1253551,838,1,"单选题","不属于主要施工管理计划的有（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","进度管理计划",false,{"key":16,"text":17,"correct":14},"B","成本管理计划",{"key":19,"text":20,"correct":14},"C","环境管理计划",{"key":22,"text":23,"correct":24},"D","绿色施工管理计划",true,"主要施工管理计划包括进度管理计划、质量管理计划、安全管理计划、环境管理计划、成本管理计划以及其他管理计划。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]