[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253540":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1253540,838,1,"单选题","案例一A公司接到B公司的施工总进度计划后，应策划价值设备安装施工接到计划：第二阶段是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","与土建工程施工全面配合阶段",false,{"key":16,"text":17,"correct":18},"B","全面安装的高峰阶段",true,{"key":20,"text":21,"correct":14},"C","安装工程由高峰转入收尾，全面进行试运转阶段",{"key":23,"text":24,"correct":14},"D","安装工程结束阶段","A公司接到B公司的施工总进度计划后，应策划价值设备安装施工接到计划：第一阶段是与土建工程施工全面配合阶段；第二阶段是全面安装的高峰阶段；第三阶段是安装工程由高峰转入收尾，全面进行试运转阶段。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]