[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253383":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1253383,837,3,"判断题","禁止承包单位将其承包的全部建筑工程转包给他人，但允许承包单位将其承包的全部建筑工程肢解以后以分包的名义分别转包给他人。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"禁止承包单位将其承包的全部建筑工程转包给他人，禁止肢解分包。",{"id":6,"name":21,"category":22,"favorite":23},"(设备安装施工)基础知识","建筑工程",0]