[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253307":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":13,"analysis":19},1253307,837,3,"判断题","施工前施工技术人员应向班组做图纸及施工技术交底。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",true,{"key":16,"text":17,"correct":18},"B","错误",false,"施工前施工技术人员应向班组做图纸及施工技术交底；施工场地及施工用水、用电等能满足施工需求；施工材料（设备）在进场后使用前应认真检查，必须符合国家标准、行业标准和有关质量、技术要求，并有产品出厂合格证。",{"id":6,"name":21,"category":22,"favorite":23},"(设备安装施工)基础知识","建筑工程",0]