[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253123":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1253123,837,2,"多选题","人工定额按表现形式的不同，可分为（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","时间定额",true,{"key":16,"text":17,"correct":18},"B","单项工序定额",false,{"key":20,"text":21,"correct":14},"C","产量定额",{"key":23,"text":24,"correct":18},"D","综合定额",{"key":26,"text":27,"correct":18},"E","分部工程定额","AC","人工定额按表现形式的不同，可分为时间定额和产量定额。产量定额*时间定额=1",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装施工)基础知识","建筑工程",0]