[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1253121":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1253121,837,2,"多选题","期间结算款包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","施工方向建设方提出申请、要求支付的款项",true,{"key":16,"text":17,"correct":14},"B","建设方按合同规则核定应该支付并同时应该收回的款项",{"key":19,"text":20,"correct":21},"C","单项工程造价",false,{"key":23,"text":24,"correct":21},"D","单位工程造价",{"key":26,"text":27,"correct":21},"E","建设资金","AB","期间结算款包括施工方向建设方提出申请、要求支付的款项和建设方按合同规则核定应该支付并同时应该收回的款项。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装施工)基础知识","建筑工程",0]