[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1252811":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1252811,837,1,"单选题","关于自动化仪表取源部件的安装要求，下列说法中正确的是（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","取源部件应在工艺设备制造或工艺管道预制、安装后进行安装",false,{"key":16,"text":17,"correct":14},"B","安装取源部件的开孑L应设置在焊缝及其边缘",{"key":19,"text":20,"correct":21},"C","温度取源部件与管道垂直安装时，取源部件轴线应与管道轴线垂直相交",true,{"key":23,"text":24,"correct":14},"D","压力取源部件应安装在温度取源部件的下游侧","取源部件的安装，应在工艺设备制造或工艺管道预制、安装的同时进行。故选项A错误。安装取源部件的开孔与焊接必须在工艺管道或设备的防腐、衬里、吹扫和压力试验前进行。应避开焊缝及其边缘。故选项B错误。压力取源部件与温度取源部件在同一管段上时，压力取源部件应安装在温度取源部件的上游侧。故选项D错误。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)基础知识","建筑工程",0]