[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1252789":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1252789,837,1,"单选题","消火栓系统施工程序中，箱体稳固的紧后工序是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","支管安装",false,{"key":16,"text":17,"correct":18},"B","附件安装",true,{"key":20,"text":21,"correct":14},"C","管道试压、冲洗",{"key":23,"text":24,"correct":14},"D","系统调试","消火栓系统施工程序：施工准备一千管安装一支管安装一箱体稳固一附件安装一管道试压、冲洗一系统调试。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)基础知识","建筑工程",0]