[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1252783":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1252783,837,1,"单选题","在消防工程中的消火栓系统施工程序中，干管安装的紧后工序是",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","附件安装",false,{"key":16,"text":17,"correct":18},"B","支管安装",true,{"key":20,"text":21,"correct":14},"C","管道试压、冲洗",{"key":23,"text":24,"correct":14},"D","系统调试","消火栓系统施工程序：施工准备、干管安装、支管安装、箱体稳固、附件安装、管道试验冲洗、系统调试。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)基础知识","建筑工程",0]