[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1252765":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1252765,837,1,"单选题","《项目管理规范》对建设工程项目的解释是：为完成依法立项的新建、扩建、改建等各类工程而进行的，有起止日期的，达到规定要求的一组相互关联的受控活动组成的特定过程，包括（ ）、勘察、设计、采购、施工、试运行、竣工验收和考核评价等，简称为项目。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","策划",true,{"key":16,"text":17,"correct":18},"B","可行性分析",false,{"key":20,"text":21,"correct":18},"C","市场调研",{"key":23,"text":24,"correct":18},"D","行业定位","《项目管理规范》对建设工程项目的解释是：为完成依法立项的新建、扩建、改建等各类工程而进行的，有起止日期的，达到规定要求的一组相互关联的受控活动组成的特定过程，包括策划、勘察、设计、采购、施工、试运行、竣工验收和考核评价等，简称为项目。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)基础知识","建筑工程",0]