[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1252733":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1252733,837,1,"单选题","机电工程项目联动试运行应由（ ）组织，并负责试运行方案的编制。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设单位",true,{"key":16,"text":17,"correct":18},"B","设计单位",false,{"key":20,"text":21,"correct":18},"C","主要设备供应商",{"key":23,"text":24,"correct":18},"D","总承包单位或施工单位","机电工程项目联动试运行由建设单位（业主）组织、指挥。建设单位工作内容包括：负责时提供各种资源，编制联动试运行方案；选用和组织试运行操作人员；实施试运行操作。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)基础知识","建筑工程",0]