[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1252725":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1252725,837,1,"单选题","电工程施工方案技术经济比较的内容不包括（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","技术的先进性",false,{"key":16,"text":17,"correct":14},"B","经济合理性",{"key":19,"text":20,"correct":14},"C","重要性",{"key":22,"text":23,"correct":24},"D","实用性",true,"机电工程施工方案的技术经济比较包括：①技术的先进性比较。比较各方案的技术水平；比较各方案的技术创新程度；比较各方案的技术效率；比较各方案实施的安全性。②经济合理性比较。比较各方案的一次性投资总额；比较各方案的资金时间价值；比较各方案对环境影响的大小；比较各方案对产值增长的贡献；比较各方案对工程进度时间及其费用影响的大小；比较各方案综合性价比。③重要性比较。推广应用的价值比较，如社会（行业）进步。社会效益的比较，如资约、污染降低等。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)基础知识","建筑工程",0]