[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1252720":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1252720,837,1,"单选题","塔、容器在安装或现场组装前应检查设备或半成品、零部件的制造质量，应符合（ ）要求方可验收。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","监理",false,{"key":16,"text":17,"correct":14},"B","业主",{"key":19,"text":20,"correct":14},"C","施工",{"key":22,"text":23,"correct":24},"D","设计",true,"塔、容器等静置设备，大多数属于非标准设备，即根据生产规模而单件设计，由制造厂生产制造成成品（设备）或半成品，由施工单位在现场安装或者组装后安装。因而主要以设计单位制定的设计文件的要求为技术质量依据。塔、容器设备或半成品、零部件在安装或现场组装前进行的制造质量检查，也应以设计文件要求为依据，符合设计要求则说明达到质量标准，才可验收。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)基础知识","建筑工程",0]