[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1252710":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1252710,837,1,"单选题","工程测量程序中，安装过程测量控制的紧前程序是",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设置沉降观测点",true,{"key":16,"text":17,"correct":18},"B","设置标高基准点",false,{"key":20,"text":21,"correct":18},"C","设置纵横中心线",{"key":23,"text":24,"correct":18},"D","建立测量控制网","工程测量的程序是：建立测量控制网→设置纵横中心线→设置标高基准点→设置沉降观测点→安装过程测量控制→实测记录。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)基础知识","建筑工程",0]