[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1252706":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1252706,837,1,"单选题","机电工程临时用电设备总容量在（ ）及以上者，均应编制临时用电施工组织设计。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","20kW",false,{"key":16,"text":17,"correct":14},"B","30kW",{"key":19,"text":20,"correct":14},"C","40kW",{"key":22,"text":23,"correct":24},"D","50kW",true,"临时用电设备在5台及其以上或设备总容量在50kW及其以上者，均应编制临时用电施工组织设计。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)基础知识","建筑工程",0]