[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1252697":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1252697,837,1,"单选题","在建筑电气防雷、接地装置的施工程序中，引下线敷设的紧后工序是（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","接地干线安装",false,{"key":16,"text":17,"correct":14},"B","避雷带安装",{"key":19,"text":20,"correct":14},"C","接地体安装",{"key":22,"text":23,"correct":24},"D","均压环安装",true,"建筑电气防雷、接地装置的施工程序：接地体安装一接地干线安装一引下线敷设一均压环安装一避雷带（避雷针、避雷网）安装。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)基础知识","建筑工程",0]