[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1252653":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1252653,837,1,"单选题","避免项目目标偏离的发生，还应重视（ ）控制，即事前分析可能导致项目目标偏离的各种影响因素，并针对这些影响因素采取有效的预防措施。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","事前主动",true,{"key":16,"text":17,"correct":18},"B","事中主动",false,{"key":20,"text":21,"correct":18},"C","事前被动",{"key":23,"text":24,"correct":18},"D","事后主动","避免项目目标偏离的发生，还应重视事前主动控制，即事前分析可能导致项目目标偏离的各种影响因素，并针对这些影响因素采取有效的预防措施。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)基础知识","建筑工程",0]