[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1252635":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1252635,837,1,"单选题","电气装置的通电检验中，逐级试通电的原则是（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","先低压后高压，先干线后支线",false,{"key":16,"text":17,"correct":14},"B","先高压后低压，先支线后干线：",{"key":19,"text":20,"correct":14},"C","先低压后高压，先支线后干线",{"key":22,"text":23,"correct":24},"D","先高压后低压，先干线后支线",true,"电气装置的通电检查步骤：①受电系统的二次回路试验合格，其保护定值已按实际要求整定完毕。受电系统的设备和电缆绝缘良好。安全警示标志和消防设施已布置到位。②按已批准的受电作业指导书，组织新建电气系统变压器高压侧接受电网侧供电，通过配电柜按先高压后低压、先干线后支线的原则逐级试通电。③试通电后，系统工作正常，可进行新建工程的试运行。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)基础知识","建筑工程",0]