[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1252631":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1252631,837,1,"单选题","消防工程安装结束后，以（ ）为主，进行消防系统的调试。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","建设单位",false,{"key":16,"text":17,"correct":14},"B","设计单位",{"key":19,"text":20,"correct":21},"C","施工单位",true,{"key":23,"text":24,"correct":14},"D","设备供应商","消防工程在施工单位安装结束后，必要时会同建设单位、设计单位和设备供应商，对固定灭火系统进行自检性质的调试检验，鉴定固定灭火系统的功能是否符合设计预期要求，发现安装缺陷，及时整改，为向公安机关消防机构申报消防验收做好准备。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)基础知识","建筑工程",0]