[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1252598":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1252598,837,1,"单选题","对于通风空调风管系统，施工单位通过系统（ ）后，即可讲人竣工验收。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","风量测定与调整",false,{"key":16,"text":17,"correct":14},"B","设备单机试运转及调整",{"key":19,"text":20,"correct":21},"C","无生产负荷联合试运转及调试",true,{"key":23,"text":24,"correct":14},"D","综合效能测定及调整","通风空调风管系统调试的主要内容包括：风量测定与调整、单机试运转、系统无生产负荷联合试运转及调试。空调系统带冷（热）源的正常联合试运转应视竣工季节与设计条件做出决定。例如，夏季可仅做带冷源试运转，冬期仅做带热源试运转。施工单位通过系统无生产负荷联合试运转与调试后，即可进入竣工验收。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)基础知识","建筑工程",0]