[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1252578":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1252578,837,1,"单选题","某工程有独立设计的施工图纸和施工组织设计，但建成后不能独立发挥生产能力，此工程应属于（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","分部分项工程",false,{"key":16,"text":17,"correct":14},"B","单项工程",{"key":19,"text":20,"correct":14},"C","分项工程",{"key":22,"text":23,"correct":24},"D","单位工程",true,"单位工程是指有独立设计的施工图纸和施工组织设计，但建成后不能独立发挥生产能力。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)基础知识","建筑工程",0]