[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1252574":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1252574,837,1,"单选题","甲单位与乙单位于2013年3月5日就某消防工程签订施工总承包合同，甲作为该工程的施工总承包单位，该工程建筑面积为20000㎡，合同约定本工程于2013年3月15日开工，开工初期，甲需采购5t角钢制作支架，角钢的供应价格为4100元\u002Ft,运费为70元\u002Ft,运输损耗0.2％，采购保管费率为1％。 乙单位需最迟在（ ）将工程预付款支付给甲单位。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","2013.3.5",false,{"key":16,"text":17,"correct":18},"B","2013.3.8",true,{"key":20,"text":21,"correct":14},"C","2013.3.15",{"key":23,"text":24,"correct":14},"D","2013.3.20","按照我国有关规定，预付款的预付时间应不迟于约定的开工日期前7天。发包方不按约定预付的，承包方在约定预付时间7天后向发包方发出要求预付的通知。合同约定本工程于2013年3月15日开工，故乙单位需最迟在2013.3.8将工程预付款支付给甲单位。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)基础知识","建筑工程",0]