[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1252570":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1252570,837,1,"单选题","《计价规范》规定，分部分项工程量清单计价应采用（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工料单价",false,{"key":16,"text":17,"correct":14},"B","定额单价",{"key":19,"text":20,"correct":21},"C","综合单价",true,{"key":23,"text":24,"correct":14},"D","全费用综合单价","根据规范规定，分部分项工程量清单计价应采用综合单价。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)基础知识","建筑工程",0]