[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1252562":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1252562,837,1,"单选题","生产某产品的工人小组由5人组成，每个小组的人员工日数为1工日，机械台班产量为4㎡\u002F工日，则时间定额应为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","0.5工日\u002F㎡",false,{"key":16,"text":17,"correct":14},"B","0.98工日\u002F㎡",{"key":19,"text":20,"correct":14},"C","1.03工日\u002F㎡",{"key":22,"text":23,"correct":24},"D","1.25工日\u002Frn2",true,"1\u002F4*5=1.25工日\u002F㎡",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)基础知识","建筑工程",0]