[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1252550":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1252550,837,1,"单选题","生产某产品的工人小组由5人组成，产量定额为2㎡\u002F工日，则时间定额应为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.5工日\u002F㎡",true,{"key":16,"text":17,"correct":18},"B","0.2工日\u002F㎡",false,{"key":20,"text":21,"correct":18},"C","0.67工日\u002F㎡",{"key":23,"text":24,"correct":18},"D","2.5工日\u002F㎡","时间定额=1\u002F产量定额，即1\u002F2=0.5工日\u002F㎡",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)基础知识","建筑工程",0]