[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1252544":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1252544,837,1,"单选题","斗容量为1m3的挖掘机9挖三类土，装车，深度3m内9小组成员2人，机械台班产量为4.8（定额单位100m3），则挖100m3的人工时间定额为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","0.19工日",false,{"key":16,"text":17,"correct":14},"B","0.38工日",{"key":19,"text":20,"correct":21},"C","0.42工日",true,{"key":23,"text":24,"correct":14},"D","1.5工日","单位产品时间定额=小组成员工日数总和\u002F机械台班产量=2\u002F4.8=0.42工日。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)基础知识","建筑工程",0]