[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1252535":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1252535,837,1,"单选题","按照《建设工程量清单计价规范》规定，工程量清单（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","必须由招标人委托具有相应资质的中介机构进行编制",false,{"key":16,"text":17,"correct":18},"B","应作为招标文件的组成部分",true,{"key":20,"text":21,"correct":14},"C","应采用工料单价计价",{"key":23,"text":24,"correct":14},"D","由总说明和分部分项工程清单两部分组成","按照《建设工程量清单计价规范》规定，工程量清单应作为招标文件的组成部分。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)基础知识","建筑工程",0]