[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1252533":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1252533,837,1,"单选题","按照生产要素内容，建设工程定额分为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","人工定额、材料消耗定额、施工机械台班使用定额",true,{"key":16,"text":17,"correct":18},"B","施工定额、预算定额、概算定额、概算指标、投资估算指标",false,{"key":20,"text":21,"correct":18},"C","国家定额、行业定额、地区定额、企业定额",{"key":23,"text":24,"correct":18},"D","建设工程定额、设备安装工程定额、建筑安装工程费用定额、工程建设其他费用定额及工具、器具定额","定额生产要素内容分类可分为人工定额、材料消耗定额、施工机械台班使用定额。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)基础知识","建筑工程",0]