[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1252531":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1252531,837,1,"单选题","按照我国有关规定，预付款的预付时间应不迟于约定的开工日期前（ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","6",false,{"key":16,"text":17,"correct":18},"B","7",true,{"key":20,"text":21,"correct":14},"C","8",{"key":23,"text":24,"correct":14},"D","9","按照我国有关规定，预付款的预付时间应不迟于约定的开工日期前7天。发包方不按约定预付的，承包方在约定预付时间7天后向发包方发出要求预付的通知。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)基础知识","建筑工程",0]