[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1252525":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1252525,837,1,"单选题","在工程造价中，工程产品具体生产过程需投入资金计划在（ ）阶段。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设计",true,{"key":16,"text":17,"correct":18},"B","概算施工图预算",false,{"key":20,"text":21,"correct":18},"C","合同造价期间",{"key":23,"text":24,"correct":18},"D","结算","在工程造价中，工程产品具体生产过程需投入资金计划在设计概算阶段。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)基础知识","建筑工程",0]