[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1252472":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1252472,837,1,"单选题","建筑给水管道安装时，干管、立管和支管的安装顺序是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","立管→干管→支管",false,{"key":16,"text":17,"correct":14},"B","支管→立管→干管",{"key":19,"text":20,"correct":21},"C","干管→立管→支管",true,{"key":23,"text":24,"correct":14},"D","立管→支管→干管","工艺流程：孔洞预留、预埋→干管（套管）安装→立管（套管）安装→支管安装→水压试验→管道防腐和保温→管道冲洗（消毒）→通水试验。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)基础知识","建筑工程",0]