[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1252157":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1252157,837,1,"单选题","在已有高程控制网的地区进行测量时，可沿用（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","国家高程基准",false,{"key":16,"text":17,"correct":14},"B","黄海高程",{"key":19,"text":20,"correct":21},"C","原高程系统",true,{"key":23,"text":24,"correct":14},"D","假定高程系统","采用国家高程基准。在已有高程控制网的地区进行测量时，可沿用原高程系统。当小测区联测有困难时，亦可采用假定高程系统。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装施工)基础知识","建筑工程",0]