[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1172059":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1172059,836,3,"判断题","柱钢筋绑扎的施工工艺流程为:调整插筋位置,套入箍筋→立柱子四个角的主筋→立柱内其余主筋→绑扎钢筋接头→将主骨架钢筋绑扎成形。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"",{"id":6,"name":21,"category":22,"favorite":23},"通用基础","建筑工程",0]