[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1171196":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1171196,835,1,"单选题","分项工程质量验收记录按( )列分目录。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","分部",false,{"key":16,"text":17,"correct":14},"B","检验批",{"key":19,"text":20,"correct":21},"C","子分部",true,{"key":23,"text":24,"correct":14},"D","分项","答案：C",{"id":6,"name":27,"category":28,"favorite":29},"岗位技能","建筑工程",0]