[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1171145":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":13,"analysis":19},1171145,834,3,"判断题","在编制施工组织总设计时，施工总进度计划与资源需求量计划编制的先后顺序关系是编制总进度计划后才可编制资源量需求量计划。（）",[11,15],{"key":12,"text":13,"correct":14},"A","正确",true,{"key":16,"text":17,"correct":18},"B","错误",false,"在编制施工组织总设计时，施工总进度计划与资源需求量计划编制的先后顺序关系是编制总进度计划后才可编制资源量需求量计划。",{"id":6,"name":21,"category":22,"favorite":23},"(资料员)专业管理实务 岗位知识","建筑工程",0]