[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1170973":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1170973,834,3,"判断题","单位工程施工完工后，先由监理单位组织预验收。（）",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"单位工程施工完工后，先由总监理工程师组织预验收。",{"id":6,"name":21,"category":22,"favorite":23},"(资料员)专业管理实务 岗位知识","建筑工程",0]