[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1170900":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1170900,834,2,"多选题","项目管理实施规划包括（）等内容。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程概况",true,{"key":16,"text":17,"correct":18},"B","项目范围管理规划",false,{"key":20,"text":21,"correct":14},"C","技术方案",{"key":23,"text":24,"correct":14},"D","进度计划",{"key":26,"text":27,"correct":14},"E","质量计划","ACDE","项目管理实施规划应包括下列内容：1项目概况。2总体工作计划。3组织方案。4技术方案。5进度计划。6质量计划。",{"id":6,"name":31,"category":32,"favorite":33},"(资料员)专业管理实务 岗位知识","建筑工程",0]