[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1170883":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1170883,834,2,"多选题","检验批的验收应按（）项目验收。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","主控",true,{"key":16,"text":17,"correct":14},"B","一般",{"key":19,"text":20,"correct":21},"C","使用",false,{"key":23,"text":24,"correct":21},"D","安全",{"key":26,"text":27,"correct":21},"E","主要","AB","检验批的验收应按主控项目和一般项目验收。",{"id":6,"name":31,"category":32,"favorite":33},"(资料员)专业管理实务 岗位知识","建筑工程",0]