[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1170782":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1170782,834,2,"多选题","施工现场应在（）前，编制地上、地下管线保护措施，由项目技术负责人组织相关人员进行审查，填写表施工现场地上、地下管线保护措施验收记录表。并报项目监理部核查。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","平整场地",true,{"key":16,"text":17,"correct":14},"B","基坑土方开挖",{"key":19,"text":20,"correct":14},"C","基槽土方开挖",{"key":22,"text":23,"correct":24},"D","垫层浇筑",false,{"key":26,"text":27,"correct":24},"E","混凝土浇筑","ABC","施工现场应在平整场地、基坑土方开挖、基槽土方开挖前，编制地上、地下管线保护措施，由项目技术负责人组织相关人员进行审查，填写表施工现场地上、地下管线保护措施验收记录表。并报项目监理部核查。",{"id":6,"name":31,"category":32,"favorite":33},"(资料员)专业管理实务 岗位知识","建筑工程",0]