[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1170749":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1170749,834,2,"多选题","项目部向甲方上报各类计划报表包括（）计划。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","月度建筑安装工程施工生产",false,{"key":16,"text":17,"correct":18},"B","月度在施工程进度",true,{"key":20,"text":21,"correct":14},"C","季度建筑安装工程施工生产",{"key":23,"text":24,"correct":18},"D","季度在施工程进度",{"key":26,"text":27,"correct":18},"E","年度施工生产进度","BDE","上报甲方各类统计报表月度在施工程进度、季度在施工程进度、年度施工生产进度。见第六章第二节P160。",{"id":6,"name":31,"category":32,"favorite":33},"(资料员)专业管理实务 岗位知识","建筑工程",0]