[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1170716":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1170716,834,2,"多选题","监理单位填写的工程延期审批表应由（）个保存一份。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","建设单位",true,{"key":16,"text":17,"correct":14},"B","施工单位",{"key":19,"text":20,"correct":14},"C","监理单位",{"key":22,"text":23,"correct":14},"D","城建档案馆",{"key":25,"text":26,"correct":27},"E","检测单位",false,"ABCD","监理单位填写的工程延期审批表应一式四份，并应由建设单位、监理单位、施工单位、城建档案馆各保存一份。",{"id":6,"name":31,"category":32,"favorite":33},"(资料员)专业管理实务 岗位知识","建筑工程",0]