[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1170655":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1170655,834,2,"多选题","需要施工单位组织专家进行论证的危险性较大的分部分项工程主要是涉及（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","深基坑",true,{"key":16,"text":17,"correct":14},"B","地下暗挖工程",{"key":19,"text":20,"correct":21},"C","起重吊装及安装拆卸工程",false,{"key":23,"text":24,"correct":14},"D","高大模板工程",{"key":26,"text":27,"correct":21},"E","拆除、爆破工程","ABD","需要施工单位组织专家进行论证的危险性较大的分部分项工程主要是涉及深基坑、地下暗挖工程、高大模板工程。",{"id":6,"name":31,"category":32,"favorite":33},"(资料员)专业管理实务 岗位知识","建筑工程",0]